Powering Rockdale County
Bringing electricity and economic prosperity to Georgia
Rockdale Energy Center is a proposed combined-cycle energy center off Hwy 212. It is early. Nothing is final, no application has been filed, and we are asking the community to help shape the plan first.
- 508-acre property
- Conceptual facility area
- Proposed community land
Conceptual layout. It will change. Explore the map
These are current estimates. They will change as studies come back, and we will update them here when they do.
What we heard at the first open house
On Thursday, October 29, neighbors came to Restoration Storehouse to see the proposal and ask questions. We heard support as well as concern. We've answered every topic raised, as far as we can today. Several studies are still underway, and the answers will be updated as they're finished.
-
The stacks
How tall will they be, and what comes out of them?
Our answerWe currently anticipate stacks of about 125 feet; final heights will be confirmed as engineering advances. More than 99.99% of what comes out is air and ordinary combustion products, mostly nitrogen and oxygen, with water vapor that can form a white plume on cold days. Read the full answer.
-
What Rockdale gets
What is the revenue estimate based on?
Our answerPublic tax revenue, not the company's operating revenue: an estimated $15.6 million for Rockdale County Public Schools and $14.2 million for Rockdale County in the first full year, and more than $300 million over the first 15 years. Read the full answer.
-
Sound and the other studies
Where do the sound and environmental studies stand?
Our answerAn independent sound study is underway, including nighttime operations. More study results will be ready to share at the December 1 open house, and others will follow as they're finished. See the list of studies.
-
Binding restrictions
Will there be binding limits on the property?
Our answerYes. The proposed zoning would prohibit data centers, battery storage, private power customers, other industrial uses, and expansion beyond the approved acreage. These remain proposals until the County acts on them. Read the full answer.
All 25 questions and answers
Property values, distance to homes, air and water, construction traffic, similar plants in Georgia, the timeline, and more.
Have a question? Ask it anytime.
Send it through the form and we'll answer you by email, usually within two business days. Common questions get added to the Questions page, and we bring them to every open house.
Nothing has been filed, approved, or built.
The first open house was held on Thursday, October 29. The second is Tuesday, December 1. We won't file a rezoning application until after it, so what we hear can shape what gets filed.
Second open house
Same place as the first. Everyone is welcome. Bring your questions.
- When
- Tuesday, December 1
5:30 to 7:30 PM - Where
- Restoration Storehouse
1400 Parker Rd SE, Conyers, GA 30094 - Entrance
- North end of the building
What's fixed
The location, and the kind of facility: a combined-cycle energy center fueled by natural gas.
What's still open
The layout, buffers and screening, the setback distance, the maximum acreage, lighting, sound mitigation, construction traffic routes, and how the community land is used.
What happens with your input
Everything sent through this site goes to the project team. We read it, and we bring it to the open houses.
It makes electricity and sends it to the public grid.
Rockdale Energy Center would generate power using combined-cycle technology, the same kind that already supplies more of Georgia's electricity than any other source. It makes electricity twice from the same fuel, which is what makes it so efficient.
- Natural gas arrives by underground pipeline and spins a turbine to make electricity.
- The leftover heat is captured and used to make steam.
- The steam spins a second turbine. More electricity, no extra fuel. The steam is then cooled with air, not water.
What it is, and what it is not
A power generator
About 1,000 megawatts of new generating capacity, added to the same grid that serves Rockdale homes and businesses. It doesn't draw power off it.
A data center
No data center would be allowed on this property, and none of the power would be set aside for one. We've proposed writing both into the zoning.
A battery storage site
No battery containers are part of this proposal.
What it would look like from the road
We drew the facility at its real size and location into views from seven roads around the property, 0.4 to 1.1 miles away. The orange outline shows where it would be. In every view, trees and hills hide all or nearly all of it. In winter, with the leaves down, a little more may show.
-
1Steeple Chase SW
0.6 mi away, looking south. Completely hidden by trees and hills.
-
2Flat Shoals Rd SW
1.0 mi away, looking southwest. About 98% hidden; at most the tip of a stack.
-
3Browns Mill Ln
0.9 mi away, looking east-southeast. Completely hidden by trees and hills.
-
4Scott Hwy (GA 212)
0.6 mi away, looking east-northeast. Completely hidden by trees and hills.
-
5Scott Hwy (GA 212)
0.4 mi away, looking north-northeast. More than 99% hidden; at most a small sliver.
-
6Scott Hwy (GA 212)
0.7 mi away, looking north-northwest. More than 99% hidden; at most a small sliver.
-
7McDaniel Mill Rd SW
1.1 mi away, looking west-northwest. Completely hidden by trees and hills.
Conceptual renderings of the October 2026 design; the final design will differ. Road photos: Google Maps. Select any view to see it full size.
A rulebook written for this one property
We are not asking for general industrial zoning, which would open the property to a long list of uses. We're asking for a planned unit development, or PUD: a zoning used to write rules for a single property.
Under it, we work with Rockdale County to spell out exactly what can be built here, where, how large, and what can never be built. The Board of Commissioners votes on those rules themselves, and they stay with the land no matter who owns it.
What we've offered to put in the rulebook so far
What it would allow
- One electric generating facility.With its connections. Today's estimate is about 45 acres. A maximum acreage is still being set; once it is, it goes in the zoning.
- A minimum setback from every neighbor.The distance is still being set. Once it is, it goes in the zoning.
- The existing forest kept as a buffer.Plus a landscaping plan approved by the county.
- Noise limits at the property line.Verified by an independent sound study.
- Community land, proposed in writing.About 165 acres south of Hwy 212 set aside for the community, proposed to be written into the zoning conditions. How it's used is still open.
What it would prohibit
- No data center of any kind.Not on any part of the 508 acres.
- No private power customer.No direct connection to a data center or any single large user. Power goes to the shared grid only.
- No expansion.Nothing beyond the approved acreage.
- No other industrial use.Now or later.
- No battery storage.None is part of this proposal, and the zoning would not allow one to be added later.
This list isn't finished. The open houses are where the rest of it gets written.
Rockdale has every reason to ask hard questions about safety.
We know what this community went through in 2024. Any new industrial neighbor should expect tougher questions because of it, and should answer them before asking for a vote. This is where we'd start.
What would you want to see in a safety plan? Tell us.
- Nothing is made here except electricity.No chemical manufacturing and no chemical warehousing.
- Every material on site is reported.Water-treatment and emissions-control materials are kept in engineered, monitored containment and reported to Rockdale County Fire and emergency management under federal right-to-know rules.
- An emergency plan written with the county.Developed with Rockdale County Fire, not handed to it, before the facility operates.
- Watched around the clock.A control room staffed 24 hours a day, automatic gas shut-off valves, built-in fire suppression, and emissions monitored continuously and reported to Georgia EPD.
What Rockdale would get
Tax estimates use current county and school millage rates and a preliminary project cost. There will be no property tax abatement. The amount is highest in the first year and steps down gradually as the equipment ages. The estimated total is more than $300 million over the first 15 years.
Proposed: about 165 acres of community land
All project land south of Hwy 212 would be set aside for the community. How it's used is still open. Ideas we've heard so far: walking and nature trails, a facility for organized sports, or leaving it as it is. See it on the map.
Revenue without the strain
The facility would add no students to the schools and use very little county service. Once operating, that means 25 to 30 employees and a limited number of routine deliveries.
Cooled with air, not water
About 150 gallons a minute, about 3.4% of what a comparable water-cooled facility would need. It would come from Rockdale's public water system, not from wells, streams, or the river.
Why this property
A facility like this can only go where two things already exist: a high-voltage transmission line and a major natural gas pipeline. This property sits between both.
That keeps new construction short and mostly on site, and it's why the facility can sit deep inside the forest instead of along the road.
What's on the map
Conceptual layout. It will change. The facility area, transmission line, and pipeline are shown in approximate locations.
The map couldn't load. In words: the 508-acre property sits on both sides of Hwy 212. The conceptual facility area is inside the forest north of the highway, the proposed community land is all project land south of it, an existing transmission line runs to the northwest, and an existing natural gas pipeline runs to the southeast.
How a decision gets made, and where you come in
Every step below has a public part. Nothing is built unless all of them are completed. Dates are targets and may shift with the county's schedule.
-
Happening now
Listening and studies
Public open houses, and the studies that answer the open questions.
- First open house held October 29. See what we heard.
- Second open house: Tuesday, December 1, 5:30 to 7:30 PM. Details.
- Questions welcome anytime, through the form
- Sound, environmental, wildlife, and cultural studies underway. More results at the December 1 open house.
- After the open houses
Application
A planned unit development (PUD) rezoning application to Rockdale County. Not filed until the open houses are done.
- Target: decision in March or April 2027
County hearings
Planning staff review, then Planning Commission and Board of Commissioners hearings. Anyone can speak.
- If approved
State air permit
A Georgia EPD review of about a year, with its own public notice and comment period.
- Target: 2031
Operation
Roughly three years of construction, beginning only after every approval.
Tell us what you think, before anything is filed.
Send your questions anytime and we'll bring the answers to the next open house. Concerns, ideas for the community land, rules you'd want written into the zoning: all of it is welcome. We read and answer every message.