This is a proposal. Nothing is final, and no zoning application has been filed. Second open house: Tuesday, December 1
Rockdale Energy Center

What we heard at the open house

Thank you to everyone who came to the Rockdale Energy Center open house on Thursday, October 29, and shared questions, comments and concerns. The proposal is still preliminary, and several engineering and environmental studies are still underway. These answers reflect what we know today. We'll update them as studies are finished and as the proposal moves through Rockdale County and state review.

Ask a question

70
About 70 people attended the open house
78
Questions and comments in all, from the open house, this site, and email, through October 31

A summary of every comment from the open house goes to Rockdale County with the rezoning application, as the county requires.

The proposal

What is being proposed?

Rockdale Energy Center is currently proposed as an approximately 1,000-megawatt combined-cycle natural gas generating facility. Combined-cycle technology generates electricity with a gas turbine and then uses the remaining heat to generate additional electricity through a steam turbine.

The electricity would be delivered to the shared public grid. The current proposal does not include a data center or battery energy storage facility.

Are similar facilities operating elsewhere in Georgia?

Yes. Combined-cycle generation is well established across the Southeast. As shown on the poster at the open house, current federal generator data identify approximately 75 operating plant sites with combined-cycle generation across Georgia and its five neighboring states, including eight separately reported facilities in Georgia.

Several Georgia facilities are in the same general size range as, or larger than, the proposed approximately 1,000-megawatt Rockdale Energy Center. Examples include:

  • McDonough-Atkinson in Cobb County: approximately 2,520 MW
  • McIntosh combined-cycle generation in Effingham County: approximately 1,319 MW
  • Thomas A. Smith Energy Facility in Murray County: approximately 1,295 MW
  • Southern Power's Wansley facility in Heard County: approximately 1,073 MW

Other operating combined-cycle facilities are located in Effingham and Heard counties. Together, these examples show that both the technology and the general scale proposed for Rockdale Energy Center are already in use in Georgia and throughout the surrounding region. The closest, Plant McDonough in Smyrna, is about 30 miles away.

Map of Georgia showing the eight operating combined-cycle natural gas facilities: Thomas A. Smith near Dalton, McDonough in Smyrna, Wansley, Wansley Unit 9 and Chattahoochee in Heard County, Mid-Georgia Cogen in Kathleen, and McIntosh and Bobby C. Smith Jr. in Effingham County, and the proposed Rockdale Energy Center east of Atlanta.Thomas A. SmithMcDonoughWansley, Wansley Unit 9& ChattahoocheeMid-Georgia CogenMcIntoshBobby C. Smith Jr.RockdaleOperating combined-cycle facilityRockdale Energy Center (proposed)
With all this land, why not build solar instead?

Solar is a growing part of Georgia's power, but it can't do this job on this land. Panels on all 508 acres would make less than a tenth of the electricity this facility would make on under 50 acres, and none at night.

Will there be binding restrictions on the property?

Yes. The project is evaluating potential PUD conditions addressing matters such as developed acreage, setbacks, buffers, sound, lighting, landscaping and future uses. The scope and specific standards would be informed by the technical studies, operational requirements and Rockdale County's review.

The current proposal contemplates prohibiting data centers, battery storage, private power customers, other industrial uses and expansion beyond the acreage approved through the zoning process. These remain proposed conditions until acted upon by the County. See the proposed rulebook.

What happens if the project does not move forward?

If the project does not receive the necessary approvals or otherwise does not proceed, the proposed generating facility would not be constructed.

If a completed facility were later retired, closure and site restoration would be addressed under the applicable permits, zoning conditions and legal requirements in effect at that time. More detailed lifecycle and decommissioning provisions will be evaluated as the project advances.

What Rockdale gets

What is the estimated annual revenue from the facility?

The current estimates refer to public tax revenue, not the company's operating revenue. Based on the preliminary project model, the first full year of operation is estimated to generate approximately:

  • $15.6 million for Rockdale County Public Schools
  • $14.2 million for Rockdale County

The combined County and school estimate is more than $300 million over the first 15 years. These figures remain preliminary and will depend on the final investment, assessed value, millage rates and equipment depreciation.

How could the project affect the existing community?

Construction activity would be managed through defined work hours, traffic controls, advance notice for major activities and measures to address dust, noise and road conditions. Operational considerations are still being evaluated through the project design and technical studies, with more detailed information to be provided as that work is completed.

Potential community benefits include new County and school tax revenue, construction activity, permanent employment and the proposed community land (final use to be determined). Both the potential benefits and impacts will be considered through the County and state review processes.

Does Rockdale need another park? What will happen with the land south of Hwy 212?

Views were split. Some of you want trails. Others told us Rockdale's parks and trails already go underused. We took both seriously. Our leading option is now a facility for organized sports. That's why we now call it community land rather than a park: it's set aside for Rockdale, and it should become something Rockdale will actually use. Tell us what you think.

What you'd see and hear

How tall will the stacks and other structures be?

The project team is confirming the height of the stacks and other major structures against the current engineering layout. We currently anticipate stacks of about 125 feet. Project siting will be a central consideration as the design moves forward. As the concept plan is refined, equipment placement, setbacks, preserved vegetation, screening and other design measures will be evaluated to limit views from nearby roadways and residences where feasible.

Final structure dimensions and locations will be provided as the engineering and permitting work advances.

What will come from the stacks, and will there be visible steam?

The primary stacks would carry turbine exhaust. Steam used within the combined-cycle process would be cooled and reused within the system. More than 99.99% of what comes out of the stack is air and ordinary combustion products. About 88% is nitrogen and oxygen, the same air the turbines draw in. Roughly 8% is water vapor, which is what forms the white plume on cold days; it is steam, not smoke. The remaining 4% or so is carbon dioxide. The trace amounts left, less than 0.01%, are the pollutants limited and monitored under the air permit, such as nitrogen oxides and carbon monoxide.

Think of the gas furnace or water heater in your home. It burns the same fuel, and its exhaust is mostly the same: the nitrogen and oxygen already in the air, water vapor and carbon dioxide. The difference is scale and cleanup. The plant runs its exhaust through catalyst systems, which work like a car's catalytic converter but are much larger and more effective, and the exhaust is measured continuously under its Georgia EPD air permit. It also gets more out of every bit of fuel: a typical car engine turns roughly a quarter to a third of its fuel into motion, while a combined-cycle plant turns about 60% into electricity.

Because natural gas combustion produces water vapor, a visible plume of steam may occasionally occur depending on weather and operating conditions. Because the project proposes air cooling, it would not have the large cooling-tower plume associated with a traditional water-cooled facility. Final exhaust characteristics will depend on the selected equipment and will be addressed through engineering and air-permitting review.

What would it look like? Will we see it from the road?

We drew the facility at its real size and location into views from seven nearby roads, and made a 360° fly-around of the property. In every road view, trees and hills hide all or nearly all of it. In winter, with the leaves down, a little more may show. See the views and the fly-around video.

What types of noise could the facility generate?

Sound will come from operating equipment as well as temporary construction and commissioning activities. An independent sound study is underway to evaluate existing conditions and anticipated project sound, including nighttime operations.

The study will help inform the final layout, mitigation measures and any appropriate project standards. Specific findings should not be assumed before that work is complete.

Environment, water and safety

What environmental or public-health impacts could result from the facility?

Like any major energy project, the facility has potential impacts that must be evaluated before it can be approved and operated. This isn't new or experimental technology. Eight combined-cycle facilities like this one already operate in Georgia, including Plant McDonough, about 30 miles away, and they are permitted and monitored under the same Georgia EPD air rules this facility would have to meet. The purpose of the project-specific studies and permitting processes is to identify those impacts, determine the standards that apply and establish appropriate controls, monitoring and mitigation.

It would be premature to characterize the project's final impacts before that work is complete. Georgia EPD's air-permitting process includes detailed technical review and the establishment of enforceable permit requirements.

How will air quality, water and the surrounding community be protected?

The facility would require state environmental review and applicable County approvals before construction or operation. The current proposal uses air-cooled technology and anticipates obtaining water from the public system rather than wells, streams or the river.

Additional project-specific information regarding air, water, sound, stormwater and other impacts will be developed through the ongoing studies and review process.

What standards and best practices would the facility follow?

The facility would be required to comply with applicable federal, state and local requirements governing its construction and operation. This would include Rockdale County development requirements, Georgia environmental permits and any project-specific conditions approved through the zoning process.

Georgia EPD's air-permitting process includes a technical review of the proposed facility and establishes applicable operating, monitoring, recordkeeping and reporting requirements.

What measures could be used to protect nearby residents?

Potential protections include the final placement of equipment, setbacks, preserved vegetation, landscaping, Best Available Control Technology (BACT) requirements, and monitoring and emergency-response planning. Appropriate standards may also be included in County approvals or state permits.

The specific measures will be informed by the technical studies, operational requirements and review by Rockdale County and the appropriate state agencies.

How will wastewater be managed, and what materials will be stored on site?

The detailed water, wastewater and materials-management plans are still being developed. Additional information will be provided as the design advances, including how wastewater would be handled and how materials needed for normal facility operations would be stored and contained.

The facility would generate electricity; it would not manufacture or warehouse chemicals. The current proposal anticipates engineered containment and applicable reporting and emergency-planning requirements for materials used on site.

What environmental studies will be conducted, and where will they be available?

Studies completed or underway include:

  • Critical Issues Analysis
  • Phase I Environmental Site Assessment
  • Threatened and Endangered Species Report
  • Wetland Delineation Report
  • Desktop Cultural Report

The project's review is expected to address the principal environmental and community issues relevant to the site, including air, sound, water, drainage, traffic, natural resources and visual impacts.

Studies required to support the rezoning request will be submitted through Rockdale County's established review process. Other engineering or state-permitting work may continue after rezoning. More results will be ready to share at the December 1 open house, and others will follow as they are finished. Plain-language updates will also be added to this website as information is finalized and appropriate for public release.

Neighbors

How close will the facility be to homes, parks and the Monastery?

The project team is preparing updated mapping showing the relationship between the proposed operating area and nearby properties and community locations.

Final distances will depend on the updated layout, setbacks and buffers. The updated map will show both the overall property boundary and the smaller area that would contain operating equipment. A minimum setback will be proposed in the rezoning application, which will be publicly available and open for public comment.

How could the project affect nearby property values?

Available research does not show a consistent or automatic effect on nearby property values. Project-specific reviews of modern natural-gas facilities have found that potential impacts may be limited when issues such as visibility, sound, traffic, lighting, setbacks and screening are appropriately addressed.

In this case, the project's more-than-500-acre site and mature wooded setting provide an opportunity to locate operating equipment farther from nearby homes and preserve substantial natural screening. That separation and vegetation may help reduce visibility, sound and other factors commonly associated with property-value concerns.

Because every property and local market is different, no specific effect can be guaranteed. The project team will continue evaluating the layout, setbacks, buffers, landscaping, lighting, sound and traffic as the design is refined.

How much construction traffic is expected?

The construction schedule and traffic assumptions are still being developed. The project team is working with its traffic consultant and Rockdale County to determine the appropriate level of traffic analysis.

Updated information will address anticipated worker and delivery traffic, potential routes, access points and measures for managing construction-related impacts. We'll share traffic estimates once the construction assumptions are developed enough to make them reliable.

Process and timeline

What is the project timeline?

The current target schedule anticipates:

  • County review and a rezoning decision in 2027
  • State air-permitting review following local approval
  • Approximately three years of construction
  • Commercial operation targeted for 2031

These are planning targets and may change based on the review process, technical studies and agency schedules.

What permits and agencies will be involved?

The project is expected to require Rockdale County land-use and development approvals, a Georgia EPD air permit and other approvals associated with construction and site development. Additional agency review may be required depending on the final design and the findings of the technical studies.

Rockdale County's process includes staff review and public hearings before the Planning Commission and Board of Commissioners. Georgia EPD's environmental permitting process also includes applicable public-notice and participation requirements.

Will the project change if the studies identify significant issues?

Yes. The studies are intended to inform the project design and identify appropriate mitigation. If they identify material issues with the current plan, the project team would evaluate potential changes to the layout, design or mitigation approach as part of the review process.

The appropriate response would depend on the specific finding, the applicable standard and the available engineering options.

How will the community continue to receive information?

The engagement process will include an additional open house on Tuesday, December 1, 2026, updates to this website, direct responses to questions, stakeholder meetings and the formal County public-hearing process. Open house details and directions.

The Georgia EPD permitting process also includes public access to permitting information and public participation where required.

Next: the second open house, Tuesday, December 1

5:30 to 7:30 PM at Restoration Storehouse in Conyers, the same place as the first. If your question isn't answered here, you don't have to wait for it.

Ask a question Details and directions